An Odoo project rarely starts on the day of the kickoff meeting. It starts in pre-sales: a few discovery meetings, a demo, a list of apps, a proposal and an opportunity marked as won in CRM. By then the client and the Odoo partner have already made many promises to each other, but most of them live in e-mails, meeting notes and people's memories.
This is the moment for a project charter: a short document, agreed by both sides, that says why the project exists, what it will deliver, who decides, and what counts as success. In this second post of the series I show what goes into a charter for an Odoo implementation, how it fits PMI's PMBOK® Guide, and how to turn it into a project in Odoo's own Project app. At the end you will find a one-page template.
What Happens Between "Won" and the Kickoff
When an Odoo opportunity is won, the work changes hands. The people who sold the project (a salesperson, a pre-sales consultant) hand it to the people who deliver it (a project manager, functional consultants, developers). On the client side, the manager who chose Odoo hands it to a project owner and key users who have to do the work alongside their daily jobs.
Without a charter, the typical problems look like this:
- Different pictures of the scope: the client remembers everything shown in the demo; the partner remembers the apps written in the proposal. Manufacturing "will come later" for one side and is "part of phase one" for the other.
- No real sponsor: the general manager signed the contract but does not attend meetings, so nobody can settle a disagreement between the finance and the warehouse teams.
- A goal that is only "move to Odoo": if the goal is the software itself, nobody can say whether the project succeeded, apart from "it is live".
- Key users who are not available: they were never told how many hours a week the project needs from them.
- A go-live date picked for the wrong reasons: the start of a fiscal year, the end of a licence or a trade fair, without checking whether data migration and training fit before it.
None of these are Odoo problems. They are problems of starting a project, and they become Odoo problems a few months later, when configuration is half done and the budget is half spent.
The PMBOK Lens: Initiating, Governance and Value
The PMBOK® Guide – Eighth Edition (PMI®, November 2025) describes the start of a project in three places. I summarise them in my own words.
- Initiating (focus area): the work that defines a project, confirms that it is worth doing and gives it formal authority to start. The classic output is the project charter. In an agile setting the same need may be covered by a vision statement and a roadmap; the point is that the project starts with an agreed purpose, not that it starts with a specific form.
- Governance (performance domain): how decisions are made, who has authority over what, and how issues are escalated. A charter is where the first governance decisions are written down: the sponsor, the project managers on both sides, and who approves scope and budget changes.
- Focus on value (principle): a project is judged by the benefits it brings, not only by the things it delivers. For an Odoo project, "the Inventory app is configured" is an output; "stock counts and the accounting value of stock agree every month" is the value the company wanted.
PMBOK does not prescribe the charter's layout. Tailor it: a 30-user Odoo rollout with Sales, Inventory and Accounting needs one page, not a 20-page document.
What Goes into an Odoo Project Charter
For an Odoo implementation I keep the charter to these headings:
- Purpose and business goals: why the company is moving to Odoo, in business terms, with two or three measurable goals and how they will be checked after go-live.
- Scope at a high level: the Odoo apps and companies in scope, the processes they cover (for example quote to cash, purchase to pay), the main integrations and the data to migrate. Also what is out of scope.
- Phases and key dates: the planned phases, the target go-live for each and the fixed dates that cannot move (a fiscal year start, a legal requirement).
- Approach: standard Odoo first; configuration before development; how developments will be delivered (for example in short sprints inside a planned phase).
- Edition, version and hosting: the Odoo version and edition the project is planned on, and where it will run. Some apps and features need Odoo Enterprise, so this is part of the scope, not a detail for later.
- Budget and how it changes: the approved budget or the basis of the estimate, and the rule for change requests.
- Roles and decisions: the client sponsor, the client project owner, the partner project manager, the key users per process area, and who signs off scope, changes and go-live.
- Time from the client team: the hours per week expected from the project owner and each key user.
- Main assumptions, constraints and risks: for example "opening balances are available from the old system by a given date", or "only one person knows the current pricing rules".
- Success and acceptance: what has to be true for go-live, and for closing the project.
- Approval: the names, dates and signatures of the sponsor and the partner.
The detailed scope comes later, from business process analysis and the fit-gap analysis. The charter only fixes the boundaries those later steps work within.
Step by Step: From the CRM Opportunity to the Project in Odoo
Labels below are from Odoo 20. CRM and Project are in both Odoo editions; where a step needs Odoo Enterprise, I say so.
1. Collect discovery in the CRM opportunity
During pre-sales, keep discovery in the opportunity, not in private notes. The Notes tab holds the client's goals and pain points, the chatter keeps meeting summaries and attached files (the proposal, process lists, sample documents), and activities track the open questions. The opportunity's Expected Revenue and Expected Closing are sales figures; they are not the project budget and the go-live date, so do not copy them into the charter without checking.
2. Draft the charter together
The partner project manager and the client project owner write the first draft together, from the opportunity's notes and the proposal. Writing it together is the point: every disagreement found now (an app that one side thought was included, a key user who has no time) is much cheaper than the same disagreement found in testing.
3. Review it with the sponsor and agree who decides
Hold one short meeting with the client sponsor to go through the charter line by line. Spend most of the time on goals, out-of-scope items and decision rights. Ask the sponsor to name the key users and confirm their time in the meeting, not after it.
4. Approve it
The sponsor and the partner sign the charter. A signature on paper, an e-mail confirmation or an electronic signature all work; what matters is that the approved version is dated and stored where both teams can find it. If you use Odoo Sign (Enterprise), the signature request and the signed PDF stay in Odoo.
5. Create the project in the Project app
Create the implementation project in Project and fill in the basics from the charter:
- At the top of the project form: the Customer, the Project Manager, the Planned Date range and tags (for example the phase).
- The Description tab: a short summary of the charter (goals, scope boundaries, key dates, decision rights), so everyone who opens the project sees it.
- The chatter: the approved charter as an attachment, with a message that it was approved and by whom. With the Documents app (Enterprise) you can also keep it in a shared project folder.
- In the Settings tab, enable Milestones and add the charter's key dates as milestones with deadlines: for example "Fit-gap approved", "UAT complete", "Go-live phase 1".
If the implementation is sold through Odoo Sales, a service product can be set to create the project when the sales order is confirmed, so the project is already linked to the order. A partner who runs many implementations can also keep a standard implementation project and use Convert to Template on it, so every new project starts with the same milestones and the same charter outline in its description.
6. Post the first project update
Open the project's Status button and create the first project update: status On Track, progress 0%, and a short note that the charter was approved and what comes next. From now on, each update can be checked against the charter: are we still inside the agreed scope, dates and budget?
Common Mistakes on Odoo Projects
- Copying the proposal and calling it a charter. A proposal lists what the partner sells; a charter records what both sides agreed to achieve and how they will decide.
- Listing apps as goals. "Implement Accounting and Inventory" is scope. "Close the month in five working days" is a goal.
- No out-of-scope list. If a topic is not written as out of scope, someone will assume it is included.
- Leaving the edition open. Choosing the edition after the fit-gap analysis can change the scope and the budget. Decide it in the charter, or write it down as an open decision with a date.
- A sponsor in name only. If the person who signs never decides anything, escalations end up with the project manager, who has no authority to settle them.
- Writing it and never opening it again. Keep the charter in the Odoo project and refer to it in project updates and change requests.
Template: a One-Page Odoo Project Charter
| Section | What to write |
|---|---|
| Project | Project name, client, Odoo partner, date and version of this charter |
| Purpose | Why the company is moving to Odoo, in two or three sentences |
| Business goals | Two or three measurable goals, and how and when each will be checked after go-live |
| In scope | Odoo apps, companies, main processes, integrations, data to migrate |
| Out of scope | Apps, processes, reports and integrations not included in this project |
| Odoo version, edition, hosting | Version, edition and where the database will run |
| Phases and milestones | Phases with target dates; dates that cannot move, and why |
| Approach | Standard first, configuration before development, how developments are delivered |
| Budget | Approved budget or estimate basis; change request rule |
| Roles | Sponsor, client project owner, partner project manager, key users per process area |
| Decisions and escalation | Who approves scope, changes, budget and go-live; where issues go when the teams disagree |
| Client time | Hours per week from the project owner and each key user |
| Assumptions and constraints | What the plan depends on |
| Main risks | The three to five biggest risks known today |
| Success and acceptance | Conditions for go-live and for closing the project |
| Approval | Sponsor and partner: name, date, signature |
Checklist Before the Kickoff
- The charter is approved, dated and attached to the project in Odoo.
- Every app in the proposal is either in scope or listed as out of scope.
- The Odoo version and edition are decided, or the decision has an owner and a date.
- The sponsor, the project owner and the key users are named, and their time is confirmed.
- The project in the Project app has a customer, a project manager, dates and the charter's milestones.
- The first project update is posted.
- The kickoff agenda starts with the charter.
In the next post I look at the people named in the charter: who does what in an Odoo implementation, with a RACI matrix for the client and partner roles.
Sources
- Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Eighth Edition, 2025: pmi.org/standards/pmbok
- Odoo 20 documentation, Project management: odoo.com/documentation
- Odoo 20 documentation, Project milestones: odoo.com/documentation
- Odoo 20 documentation, Project dashboard and project updates: odoo.com/documentation
- Odoo 20 documentation, CRM: odoo.com/documentation